Background

The customer is an American steel sheet producer with multiple locations throughout the US. They are the largest and most diverse supplier of steel, serving industries such as:

  1. Construction
  2. Automotive
  3. Infrastructure
  4. Oil & Gas
  • Transportation
  • Agriculture
  • Energy Generation
  • Transmission & Heavy Equipment

The Avon Engineering team was called upon to develop a solution for the steel operations that would reduce downtime.

Problem

Ladle beams are specialized lifting devices used in steel mills and foundries to handle ladles containing molten metal. These high capacity systems are used to transport molten metal 24 hours a day, 7 days per week in the steel production operation. Ladle beams typically incorporate multiple sheaves, or pulleys, and bearings that are reeved directly into the crane.

When a sheave or bearing fails, or the beam requires servicing, the operation comes to a halt as it must be removed from the crane for servicing. This involves unreeving of the wire rope from which the beam is suspended from the crane. The result is downtime of up to 20 hrs, which in turn means loss of production and revenue.

Lifting Machine Before

Solution

The Avon Engineering team was able to improve the customer’s process by modifying the existing beam and how the sheaves are mounted. Sheaves are normally mounted between upright plates welded to the beam. The Avon redesign has the sheaves housed in baskets separate from the beam which are suspended from the crane. The beam can now directly be pinned to the baskets or replaced quickly without having to unreeve the wire rope. Using our design software, we performed a stress analysis to ensure the safety and reliability of this new system.

The next phase of the project involved determining how to remove the baskets suspended from the crane without removing the wire rope. Our team devised a solution by bolting the side stiffener plates rather than welding them. This enables the plates to be removed quickly, and the wire rope dropped down below the basket and moved out to the side. New baskets with sheaves and bearings can now be installed quickly.

Lifting Machine After

Results

The new beam handling system has resulted in tremendous productivity gains for the steel operation. The removal and installation of the beam was reduced from 20 hrs to only 6 hrs. Our solution has provided ease of maintenance and repair as well as a significant reduction in downtime, saving the customer time and money.

The Avon Engineering team has modified a total of 7 beam systems for multiple customers, and we are currently working on 2 more.